Engagement Retrospective: Northstar Telecom Hybrid POC

Based on: Engagement Retrospective Template
Date: 2026-05-01
Duration: 2026-04-01 to 2026-04-30
Type: POC
Environment: Hybrid


Summary

Northstar Telecom completed a hybrid POC connecting an on-prem Kubernetes lab to cloud-hosted control services. The POC met its primary success criteria for connectivity, identity integration, and telemetry ingestion, but firewall approval delays compressed the final validation window.


What Went Well

  • Weekly customer-facing status emails kept the platform, network, and operations teams aligned.
  • The early environment validation checklist surfaced DNS and certificate gaps before deployment week.
  • Using sanitized telemetry data let the customer validate workflows without waiting for production data approvals.

What Could Have Gone Better

  • Firewall requests were submitted after kickoff instead of during pre-kickoff planning.
  • The runbook owner was unclear until the final week.
  • Load testing depended on a single network engineer being available for packet capture validation.

Root Causes

  • We treated network approvals as implementation tasks instead of long-lead prerequisites.
  • Success criteria named technical outcomes but did not assign operational artifact owners.
  • The customer had separate platform and network teams, but our project plan assumed one infrastructure workstream.

Action Items

ActionApply To
Add firewall and DNS approval dates to the POC plan before kickoff.Hybrid and firewall-restricted POCs
Assign an owner for each operational artifact during kickoff.All implementations
Identify backup approvers for network validation tasks.Telecom and other matrixed infrastructure teams

Artifacts Worth Saving

  • Sanitized telemetry replay script used for ingestion validation.
  • Hybrid connectivity test checklist.
  • Customer-facing runbook outline for operations handoff.

Notes

The customer responded well to concise written summaries with explicit owner and due-date fields. Continue using a weekly email cadence even when Slack is active.